(WATERBURY, CT) The City of Waterbury Engineering Department has announced the approximate milling and paving schedule for the next two weeks, November 2 through November 13, weather permitting.
Motorists should anticipate delays and possible detours in the affected areas and are encouraged to consider alternate routes. On-street parking will be prohibited during working hours, from 7 a.m. to 6 p.m., on streets where work is taking place.
The anticipated schedule is as follows:
Monday, November 2
· Frost Road: Concrete ramp installation
· Sharon Road: Paving
Tuesday, November 3
· Frost Road: Concrete ramp installation
· Windy Drive: Paving
Wednesday, November 4
· Frost Road: Concrete ramp installation
· Windy Drive, Windy Drive Extension, Boland Drive, Blue Trail Drive and Ferrone Avenue: Paving
Thursday, November 5
· Frost Road: Concrete ramp installation
· Woodtick Road: Paving
Friday, November 6
· Frost Road: Concrete ramp installation
· Woodtick Road: Paving
Monday, November 9
· Woodtick Road, Selah Street and Frost Road: Paving
· Frost Road: Milling
Tuesday, November 10
· Frost Road: Paving
· Frost Road and Pearl Lake Road: Milling
Wednesday, November 11
· Frost Road: Paving
· Pearl Lake Road and Merritt Street: Milling
Thursday, November 12
· Pearl Lake Road and Merritt Street: Paving
· Pierpont Road, Luke Street, Keefe Street and Fairmount Street: Milling
Friday, November 13
· Pearl Lake Road, Pierpont Road, Luke Street, Keefe Street and Fairmount Street: Paving
The schedule is approximate and subject to change based on weather and field conditions.
Residents with questions regarding the paving program may contact the Engineering Department at 203-574-6851.