Waterbury Announces Updated Milling and Paving Schedule for November 2–13

The Waterbury Times|Nov 3, 2026

(WATERBURY, CT) The City of Waterbury Engineering Department has announced the approximate milling and paving schedule for the next two weeks, November 2 through November 13, weather permitting.

Motorists should anticipate delays and possible detours in the affected areas and are encouraged to consider alternate routes. On-street parking will be prohibited during working hours, from 7 a.m. to 6 p.m., on streets where work is taking place.

The anticipated schedule is as follows:

Monday, November 2

·         Frost Road: Concrete ramp installation

·         Sharon Road: Paving

Tuesday, November 3

·         Frost Road: Concrete ramp installation

·         Windy Drive: Paving

Wednesday, November 4

·         Frost Road: Concrete ramp installation

·         Windy Drive, Windy Drive Extension, Boland Drive, Blue Trail Drive and Ferrone Avenue: Paving

Thursday, November 5

·         Frost Road: Concrete ramp installation

·         Woodtick Road: Paving

Friday, November 6

·         Frost Road: Concrete ramp installation

·         Woodtick Road: Paving

Monday, November 9

·         Woodtick Road, Selah Street and Frost Road: Paving

·         Frost Road: Milling

Tuesday, November 10

·         Frost Road: Paving

·         Frost Road and Pearl Lake Road: Milling

Wednesday, November 11

·         Frost Road: Paving

·         Pearl Lake Road and Merritt Street: Milling

Thursday, November 12

·         Pearl Lake Road and Merritt Street: Paving

·         Pierpont Road, Luke Street, Keefe Street and Fairmount Street: Milling

Friday, November 13

·         Pearl Lake Road, Pierpont Road, Luke Street, Keefe Street and Fairmount Street: Paving

The schedule is approximate and subject to change based on weather and field conditions.

Residents with questions regarding the paving program may contact the Engineering Department at 203-574-6851.